Worth a lookThe county is undertaking Phase 2 to amend and update the 2019 General Plan and Zoning Ordinance to address data centers, electric substations, on-site power generation uses, battery energy storage systems, and microgrids.
Loudoun County, VA · Rezoning / zoning · detected Jul 8, 2026, 8:30 AM UTC
Signal strength75/100
“Amend and update 2019 GP and Zoning Ordinance to address: o Data Centers o Electric Substations o On-Site Power Generation Uses o Battery Energy Storage Systems (BESS) o Microgrids”
Quoted verbatim from the public record; original spelling preserved. Canonical location: Loudoun County, VA.
- County
- Loudoun
- Meeting date
- Jun 30, 2026
- Meeting
- Joint Board of Supervisors/Planning Commission Special Business Meeting - Jun 30, 2026
- Need number
- 284785
- Project
- Data Center Standards and Locations, Phase 2