Worth a lookThe Planning Commission considered a Commission Permit and Special Exception to permit a Utility, Major (utility substation) in the General Industrial (GI) Zoning District, and a Minor SPEX to modify buffer requirements.
Loudoun County, VA · Rezoning / zoning · detected Jul 8, 2026, 8:30 AM UTC
Signal strength75/100
“Darby Metcalf, with the Department of Planning and Zoning, gave a presentation to the Planning Commission to consider a Commission Permit (CMPT) and Special Exception (SPEX) to permit a Utility, Major (utility substation) in the General Industrial (GI) Zoning District, and a Minor SPEX to modify buffer requirements.”
Quoted verbatim from the public record; original spelling preserved. Canonical location: Loudoun County, VA.
- Case number
- SPEX-2025-0016
- County
- Loudoun
- Meeting date
- Jun 23, 2026
- Meeting
- Planning Commission Public Hearing - Jun 23, 2026
- Project
- Tech Park at Dulles Substation
- State
- VA
Why now
A rezoning or special-exception filing signals a project entering the approval pipeline, usually 6 to 12 months ahead.