New data-center load request: Harlem in Hanover County, VA (100.0 MW).

Hanover County, VA · Load request · detected Aug 28, 2026, 5:35 PM UTC

Signal strength70/100
DEV Distribution has previously submitted a DP Request for a new substation (Harlem) to serve a data center in Hanover County with a total load in excess of 100MW. The requested in-service date is 01/01/2029. Load is expected to exceed 100MW in 2032. The DP request was withdrawn. Initial In-Service Load Projected 2029 Load Summer: 4.5 MW Summer: 4.5 MW Harlem Sub Winter: 3.7 MW Winter: 3.7 MW 230kV Delivery TEAC – Dominion Supplemental 9/08/2026

Quoted verbatim from the public record; original spelling preserved. Canonical location: Hanover County, VA.

County
Hanover
Target in service
01/01/2029
Jurisdiction type
county
Meeting date
Sep 8, 2026
Capacity (MW)
100
Need number
DOM-2024-0067
Project
Harlem
State
VA
Status
need

Why now

Power and cooling vendors typically engage within 90 days of a new data-center load request.

Matter history

  1. Sep 8, 2026 · Load requestscheduled, hasn't happened yet

    New data-center load request: Harlem in Hanover County, VA (100.0 MW).