Worth a lookNew data-center load request: James Hill in Petersburg, VA (100.0 MW).
Petersburg, VA · Load request · detected Jun 16, 2026, 7:47 AM UTC
Signal strength70/100
“DEV Distribution has submitted a DP Request for a new substation (James Hill James Hill Sub Jamestown Drive) to serve a data center in Petersburg, VA with a total load in excess 230kV Delivery of 100 MW. The requested in-service date is 12/31/2028. TEAC – Dominion Supplemental 02/03/2026 4”
Quoted verbatim from the public record; original spelling preserved. Canonical location: Petersburg, VA.
- County
- Petersburg
- Target in service
- 12/31/2028
- Meeting date
- Feb 3, 2026
- Capacity (MW)
- 100
- Need number
- DOM-2024-0036
- Project
- James Hill
- State
- VA
- Status
- solution
Why now
Power and cooling vendors typically engage within 90 days of a new data-center load request.