New data-center load request: James Hill in Petersburg, VA (100.0 MW).

Petersburg, VA · Load request · detected Jun 16, 2026, 7:47 AM UTC

Signal strength70/100
DEV Distribution has submitted a DP Request for a new substation (James Hill James Hill Sub Jamestown Drive) to serve a data center in Petersburg, VA with a total load in excess 230kV Delivery of 100 MW. The requested in-service date is 12/31/2028. TEAC – Dominion Supplemental 02/03/2026 4

Quoted verbatim from the public record; original spelling preserved. Canonical location: Petersburg, VA.

County
Petersburg
Target in service
12/31/2028
Meeting date
Feb 3, 2026
Capacity (MW)
100
Need number
DOM-2024-0036
Project
James Hill
State
VA
Status
solution

Why now

Power and cooling vendors typically engage within 90 days of a new data-center load request.