← Back to feed

Signal · GridFreeze

Worth a look

New data-center load request: James Hill in Petersburg County, VA (100.0 MW).

Petersburg County, VA · Load request · detected Jun 16, 2026, 7:47 AM UTC

70

Confidence: 100%

DEV Distribution has submitted a DP Request for a new substation (James Hill James Hill Sub Jamestown Drive) to serve a data center in Petersburg, VA with a total load in excess 230kV Delivery of 100 MW. The requested in-service date is 12/31/2028. TEAC – Dominion Supplemental 02/03/2026 4
county
Petersburg
in_service
12/31/2028
meeting_date
2026-02-03
mw
100
need_number
DOM-2024-0036
pdf_url
https://www.pjm.com/-/media/DotCom/committees-groups/committees/teac/2026/20260203/20260203-item-12---dom-supplemental-projects.pdf
project_name
James Hill
state
VA
status
solution

Why now

Power and cooling vendors typically engage within 90 days of a new data-center load request.

View source ↗

Every signal links to the public record it came from.