New data-center load request: Atlas in Prince William County, VA (100.0 MW).

Prince William County, VA · Load request · detected Aug 11, 2026, 2:51 PM UTC

Signal strength70/100
DEV Distribution has submitted a DP Request for a new substation (Atlas) to serve a data center complex in Gainesville with a total load in excess of 100 MW. Requested in-service date is 04/01/2028. Initial In-Service Load Projected 2028 Load Summer: 70.0 MW Summer: 70.0 MW Winter: 0.0 MW Winter: 0.0 MW TEAC – Dominion Supplemental 08/04/2026

Quoted verbatim from the public record; original spelling preserved. Canonical location: Prince William County, VA.

County
Prince William
Target in service
04/01/2028
Jurisdiction type
county
Meeting date
Aug 4, 2026
Capacity (MW)
100
Need number
DOM-2023-0011
Project
Atlas
State
VA
Status
need

Why now

Power and cooling vendors typically engage within 90 days of a new data-center load request.