New data-center load request: Shaw in Culpeper County, VA (300.0 MW).

Culpeper County, VA · Load request · detected Aug 11, 2026, 3:18 PM UTC

Signal strength80/100
REC has submitted a DP request for a new 230 kV delivery point (Shaw) to serve a data center customer in Culpeper County, VA with a total expected load of 300 MW. Line #2 Expected target date is 05/01/2028. TEAC – Dominion Supplemental 01/06/2026 14

Quoted verbatim from the public record; original spelling preserved. Canonical location: Culpeper County, VA.

County
Culpeper
Jurisdiction type
county
Meeting date
Jan 6, 2026
Capacity (MW)
300
Need number
DOM-2025-0070
Project
Shaw
State
VA
Status
solution

Why now

Power and cooling vendors typically engage within 90 days of a new data-center load request.