Worth a lookNew data-center load request: Frances in Louisa County, VA (176.0 MW).
Louisa County, VA · Load request · detected Aug 11, 2026, 3:18 PM UTC
Signal strength70/100
“Frances 230 kV REC has submitted a DP request for a new 230 kV delivery point (Frances) Delivery to serve a data center customer in Louisa County, VA with a total expected load of 176 MW. Expected target date is 08/01/2027. TEAC – Dominion Supplemental 01/06/2026 16”
Quoted verbatim from the public record; original spelling preserved. Canonical location: Louisa County, VA.
- County
- Louisa
- Jurisdiction type
- county
- Meeting date
- Jan 6, 2026
- Capacity (MW)
- 176
- Need number
- DOM-2025-0071
- Project
- Frances
- State
- VA
- Status
- solution
Why now
Power and cooling vendors typically engage within 90 days of a new data-center load request.