Worth a lookNew data-center load request: Emy in Spotsylvania County, VA (212.0 MW).
Spotsylvania County, VA · Load request · detected Jun 16, 2026, 7:47 AM UTC
Signal strength80/100
“Emy Sub Rappahannock Electric Cooperative (REC) has submitted a DP Request for a new 230kV Delivery - REC substation (Emy) to serve a data center in Spotsylvania County, VA with a total expected capacity of 212 MW. The requested in-service date is 07/05/2027. TEAC – Dominion Supplemental 02/03/2026 6”
Quoted verbatim from the public record; original spelling preserved. Canonical location: Spotsylvania County, VA.
- County
- Spotsylvania
- Target in service
- 07/05/2027
- Meeting date
- Feb 3, 2026
- Capacity (MW)
- 212
- Need number
- DOM-2025-0051
- Project
- Emy
- State
- VA
- Status
- solution