Signal · GridFreeze
Act this weekNew data-center load request: Guss in Louisa County, VA (259.6 MW).
Louisa County, VA · Load request · detected Jun 16, 2026, 7:47 AM UTC
80
Confidence: 100%
“REC has submitted a DP request for a new 230 kV delivery point (Guss) to serve a data center customer in Louisa County, VA with a total expected capacity of 259.6 MW. The requested in-service date is 12/31/2032. Guss - 230 kV Delivery TEAC – Dominion Supplemental 03/10/2026 3”
- county
- Louisa
- in_service
- 12/31/2032
- meeting_date
- 2026-03-10
- mw
- 259.6
- need_number
- DOM-2026-0010
- pdf_url
- https://www.pjm.com/-/media/DotCom/committees-groups/committees/teac/2026/20260310/20260310-item-09---dom-supplemental-projects.pdf
- project_name
- Guss
- state
- VA
- status
- need
Why now
Power and cooling vendors typically engage within 90 days of a new data-center load request.