Worth a lookNew data-center load request: Guss in Louisa County, VA (259.6 MW).
Louisa County, VA · Load request · detected Jun 16, 2026, 7:47 AM UTC
Signal strength80/100
“REC has submitted a DP request for a new 230 kV delivery point (Guss) to serve a data center customer in Louisa County, VA with a total expected capacity of 259.6 MW. The requested in-service date is 12/31/2032. Guss - 230 kV Delivery TEAC – Dominion Supplemental 03/10/2026 3”
Quoted verbatim from the public record; original spelling preserved. Canonical location: Louisa County, VA.
- County
- Louisa
- Target in service
- 12/31/2032
- Meeting date
- Mar 10, 2026
- Capacity (MW)
- 259.6
- Need number
- DOM-2026-0010
- Project
- Guss
- State
- VA
- Status
- need
Why now
Power and cooling vendors typically engage within 90 days of a new data-center load request.