New data-center load request: Simms in King George County, VA (296.0 MW).

King George County, VA · Load request · detected Jun 16, 2026, 7:48 AM UTC

Signal strength80/100
ODEC on behalf of NNEC has submitted a DP Request for a new substation (Simms) to serve a data center campus in Kings Geroge County, VA with a total expected Simms 230kV capacity of 296MW. Delivery Requested in-service date is 12/01/2029. TEAC – Dominion Supplemental 04/07/2026 4

Quoted verbatim from the public record; original spelling preserved. Canonical location: King George County, VA.

County
King George
Target in service
12/01/2029
Meeting date
Apr 7, 2026
Capacity (MW)
296
Need number
DOM-2026-0015
Project
Simms
State
VA
Status
need

Why now

Power and cooling vendors typically engage within 90 days of a new data-center load request.