Signal · GridFreeze
Worth a lookNew data-center load request: Firehouse in Loudoun County, VA (100.0 MW).
Loudoun County, VA · Load request · detected Jun 16, 2026, 7:48 AM UTC
Signal strength70/100
“DEV Distribution has submitted a DP request for a new substation (Firehouse) to serve a data center complex in Loudoun County with a total load in excess of 100 MW. Requested in-service date is 01/31/2028 12/31/2030. Initial In-Service Load Projected 2030 Load Summer: 209 MW Summer: 234 MW Winter: 160 MW Winter: 234 MW TEAC – Dominion Supplemental 04/07/2026 11”
Quoted verbatim from the public record; original spelling preserved. Canonical location: Loudoun County, VA.
- County
- Loudoun
- Target in service
- 01/31/2028
- Meeting date
- Apr 7, 2026
- Capacity (MW)
- 100
- Need number
- DOM-2024-0016
- Project
- Firehouse
- State
- VA
- Status
- solution
Why now
Power and cooling vendors typically engage within 90 days of a new data-center load request.