Act this weekNew data-center load request: Stockholm in Henrico County, VA (300.0 MW).
Henrico County, VA · Load request · detected Jun 16, 2026, 7:48 AM UTC
80
Confidence: 100%
“DEV Distribution has submitted a DP Request for a new substation (Stockholm) to serve a data center in Henrico County with a total load of 300 MW. The target date is Q4 2028. TEAC – Dominion Supplemental 05/08/2026 8”
- county
- Henrico
- meeting_date
- 2026-05-08
- mw
- 300
- need_number
- DOM-2024-0049
- pdf_url
- https://www.pjm.com/-/media/DotCom/committees-groups/committees/teac/2026/20260508/20260508-item-09---dom-supplemental-projects.pdf
- project_name
- Stockholm
- state
- VA
- status
- solution
Why now
Power and cooling vendors typically engage within 90 days of a new data-center load request.