New data-center load request: Mudel in Prince William County, VA (300.0 MW).

Prince William County, VA · Load request · detected Jun 16, 2026, 7:49 AM UTC

Signal strength80/100
NOVEC has submitted a DP Request for a new substation (Mudel) for split-use service of residential, commercial, and a new data center complex in Prince William County, VA with a total expected capacity of 300 MW. Mudel 230 kV Delivery – NOVEC Expected in-service date is 12/30/2029. TEAC – Dominion Supplemental 06/02/2026

Quoted verbatim from the public record; original spelling preserved. Canonical location: Prince William County, VA.

County
Prince William
Target in service
12/30/2029
Meeting date
Jun 2, 2026
Capacity (MW)
300
Need number
DOM-2026-0025
Project
Mudel
State
VA
Status
need

Why now

Power and cooling vendors typically engage within 90 days of a new data-center load request.