GridFreeze · County Watch

Where data centers meet the local fight

A running read on data-center development across the counties that decide it: the votes, the zoning, the grid load. Every line below links to the public record.

This page is the current week. Read the back issues.

Data refreshed Aug 21, 2026

Share

Our national sweep has reached 13 jurisdictions across 6 states. In total, 18 jurisdictions show active data-center matters on the public record. Here's where the fights are.

53

governance actions on data centers

3,726 MW

of data-center load requested

300 MW

largest single request

16

jurisdictions tracked

Computed live from the public record, since Jul 2024.

Get County Watch every Friday

One email a week: the governance votes, zoning cases and grid load that moved, each linked to the public record it came from.

Free. One email a week. Unsubscribe from any of them.

We alert the day we detect a matter. Over the last 60 days detection ran a median of 2worst case of 14. Speed varies by source, and every alert prints its own measured lag so you can check it. Next business day is the engineering target.

Loudoun County, VA: the standards fight

Data Center Alley is also where the rules are being rewritten: standards votes, rezonings, and substation cases that decide what gets built next.

Rezoning / zoning · Loudoun County, VA

Worth a look

A bill was introduced to allow localities to consider the impacts of high-energy users on the electric grid in zoning decisions.

Detected Jul 25, 2026 · case 285852

What changed
Rezoning filed in Loudoun County · Reconvened July 21, 2026, Board of Supervisors Business Meeting, Jul 22, 2026 · case 285852
Why now
A rezoning or special-exception filing signals a project entering the approval pipeline, usually 6 to 12 months ahead.
View source record ↗
1 earlier update for this matter

Rezoning / zoning · Loudoun County, VA

Worth a look

The applicant is requesting a Special Exception to permit data center use in moderately steep slopes.

Detected Jul 24, 2026 · case SPEX-2025-0054

What changed
Rezoning filed in Loudoun County · Planning Commission Public Hearing, Jul 23, 2026 · case SPEX-2025-0054
Why now
A rezoning or special-exception filing signals a project entering the approval pipeline, usually 6 to 12 months ahead.
View source record ↗
2 earlier updates for this matter

Rezoning / zoning · Loudoun County, VA

Worth a look

The application seeks to rezone 10.08 acres from the Planned Development – Research and Development Park to the PD-RDP Legacy Zoning District.

Detected Jul 22, 2026 · case ZMAP-2025-0019

What changed
Rezoning filed in Loudoun County · Board of Supervisors Public Hearing, Jul 15, 2026 · case ZMAP-2025-0019
Why now
A rezoning or special-exception filing signals a project entering the approval pipeline, usually 6 to 12 months ahead.
View source record ↗

Governance / standards · Loudoun County, VA

Worth a look

Staff supports a recommendation of approval to the Board of Supervisors.

Detected Jul 10, 2026 · case ZMAP-2024-0018

What changed
Standards / approval adopted in Loudoun County · Planning Commission Work Session and Public Hearing, Jul 9, 2026 · case ZMAP-2024-0018
Why now
Adopted standards reshape what's buildable in the jurisdiction.
View source record ↗
4 earlier updates for this matter

Rezoning / zoning · Loudoun County, VA

Worth a look

The purpose of this item is to consider a Commission Permit (CMPT) and Special Exception (SPEX) to permit a Utility, Major (utility substation) in the Industrial Park (IP) Zoning District.

Detected Jun 22, 2026 · case SPEX-2025-0032

What changed
Rezoning filed in Loudoun County · Planning Commission Public Hearing, May 26, 2026 · case SPEX-2025-0032
Why now
A rezoning or special-exception filing signals a project entering the approval pipeline, usually 6 to 12 months ahead.
View source record ↗
1 earlier update for this matter

Governance / standards · Loudoun County, VA

Worth a look

A Special Exception to establish the Aspen Substation (Utility, Major) and related SPEX modifications is being considered for approval by the Board subject to Conditions of Approval.

Detected Jul 9, 2026 · case 285166

What changed
Standards / approval adopted in Loudoun County · Board of Supervisors Business Meeting, Jul 7, 2026 · case 285166
Why now
Adopted standards reshape what's buildable in the jurisdiction.
View source record ↗
4 earlier updates for this matter

Rezoning / zoning · Loudoun County, VA

Worth a look

The Board of Supervisors and Planning Commission will discuss proposed standards and locations for data centers.

Detected Jul 8, 2026 · case 284763

What changed
Rezoning filed in Loudoun County · Joint Board of Supervisors/Planning Commission Special Business Meeting, Jun 30, 2026 · case 284763
Why now
A rezoning or special-exception filing signals a project entering the approval pipeline, usually 6 to 12 months ahead.
View source record ↗

Governance / standards · Loudoun County, VA

Worth a look

Data Centers were designated as a Conditional Use in the Loudoun County 2019 General Plan.

Detected Jul 8, 2026 · case 284785

What changed
Standards / approval adopted in Loudoun County · Joint Board of Supervisors/Planning Commission Special Business Meeting, Jun 30, 2026 · case 284785
Why now
Adopted standards reshape what's buildable in the jurisdiction.
View source record ↗
1 earlier update for this matter

Rezoning / zoning · Loudoun County, VA

Worth a look

The Planning Commission considered a Commission Permit and Special Exception to permit a Utility, Major (utility substation) in the General Industrial (GI) Zoning District, and a Minor SPEX to modify buffer requirements.

Detected Jul 8, 2026 · case SPEX-2025-0016

What changed
Rezoning filed in Loudoun County · Planning Commission Public Hearing, Jun 23, 2026 · case SPEX-2025-0016
Why now
A rezoning or special-exception filing signals a project entering the approval pipeline, usually 6 to 12 months ahead.
View source record ↗
2 earlier updates for this matter

Rezoning / zoning · Loudoun County, VA

Worth a look

The applicant is requesting a Zoning Map Amendment to rezone 117.07 acres from JLMA-3 to PD-IP to allow for a business/industrial park with up to 986,000 square feet of industrial uses.

Detected Jun 22, 2026 · case ZMAP-2023-0008

What changed
Rezoning filed in Loudoun County · Board of Supervisors Business Meeting, Jun 2, 2026 · case ZMAP-2023-0008
Why now
A rezoning or special-exception filing signals a project entering the approval pipeline, usually 6 to 12 months ahead.
View source record ↗
1 earlier update for this matter

Governance / standards · Loudoun County, VA

Worth a look

At the Board Business Meeting on March 18, 2025, the Board adopted (7-2: Kershner and Umstattd opposed) Phase 1 and the Grandfathering Resolution (5-4: Briskman, Glass, TeKrony, and Turner opposed).

Detected Jun 17, 2026 · case 267140

What changed
Standards / approval adopted in Loudoun County · BOS Jul 28 2025 - Data Center Standards Phase 2, Jul 28, 2025 · case 267140
Why now
Adopted standards reshape what's buildable in the jurisdiction.
View source record ↗
1 earlier update for this matter

The Virginia load pipeline

Behind the votes, the demand: 16 data-center load requests totalling about 3,726 MW now moving through the grid queue.

Texas: the model travels

The same playbook, a new state: Mesquite (Dallas metro) writing data-center development standards, pulled straight from the public record.

Governance / standards · Austin, TX

Worth a look

Austin, TX City Council Work Session: Briefing on the current status of data center uses in the City and possible future amendments to the City Code or regulations. [Joi Harden, Acting Assistant Director - Austin Planning, Shay Roalson, Director - Austin Water, Stuart Reilly, General Manager - Austin Energy]. (Agenda Ready).

Detected Aug 19, 2026 · case 26-2407

What changed
Standards / approval adopted in Austin · City Council Work Session, Aug 11, 2026 · case 26-2407
Why now
Adopted standards reshape what's buildable in the jurisdiction.
View source record ↗

Governance / standards · Austin, TX

Worth a look

Austin, TX City Council: Approve a resolution initiating amendments to City Code Title 25 (Land Development Code) and other provisions of City Code or regulations necessary to establish land uses, site development regulations, and development processes, for data center use in certain zoning districts and to develop business regulations and permit requirements applicable to data center operations. Funding: This item has no fiscal impact. (Agenda Ready).

Detected Aug 18, 2026 · case 26-2329

What changed
Standards / approval adopted in Austin · City Council, Aug 5, 2026 · case 26-2329
Why now
Adopted standards reshape what's buildable in the jurisdiction.
View source record ↗

Governance / standards · Mesquite, TX

Worth a look

Mesquite, TX City Council: Data Center Development Standards (Pre-Meeting).

Detected Jun 22, 2026 · case 26-8210

What changed
Standards / approval adopted in Mesquite · City Council, Apr 16, 2026 · case 26-8210
Why now
Adopted standards reshape what's buildable in the jurisdiction.
View source record ↗
1 earlier update for this matter

For completeness: 3 generation/storage items also sit in the ERCOT queue for Texas - grid context, not a data-center load.

What you get

  • Your market's signals. Governance votes, data-center load requests, and zoning for the counties you cover.

  • A weekly email digest. The new signals for your market, summarized, straight to your inbox.

  • Every signal source-linked. Each one links to the public record, so you can verify it yourself.

Want this for your market?

County Watch tracks every market we cover. Drop your email to get the signals for your accounts, before they're news.

Track my market

Prefer email only? Get the weekly digest: